ERM was contracted to carry out electrical and instrumentation works for a client in the Pilbara region of Western Australia. The scope of work included the cutover of HV and Control Assets to the new Pumping Station. The works were designed, planned and carried out during a planned Plant Shutdown activity.
ERM completed the works and performed Stage 1 – Stage 4 Commissioning activities safely and well within the shutdown timeframe.
Scope
ERM was responsible for the complete execution of the works, including providing all goods and services required for the project. This includes material, labour, supervision, tools, and testing equipment.
Conclusion
ERM successfully completed the electrical and instrumentation works for the client in the Pilbara region of Western Australia. The scope of work encompassed:
- Installation of electrical assets (such as cabling, HV terminations and control system equipment).
- Testing and ready for commissioning activities, strictly following the Test | Commissioning plan.
- Commissioning activities – Stage 1 – Stage 4.
The project was executed safely in accordance with the project requirements and timeline. All necessary works and verification processes were executed to ensure a successful outcome for the client and ERM.